Question
Chain Company has developed the following data from its Material A: Safety stock 280 units Average daily usage 200 units EOQ 1,000 units Cost of
Chain Company has developed the following data from its Material A:
Safety stock 280 units
Average daily usage 200 units
EOQ 1,000 units
Cost of placing one order P 20
Working days per year 250 days
Lead time 6 days
21) What is the reorder point? A. 1,480 B. 1,720 C. 1,360 D. 2,200
22) What is the absolute maximum inventory? A.1,280 units B. 800 units C.1,040 units D.1,400 units
23) What is the normal maximum inventory? A.1,280 units B.1,400 units C. 800 units D.1,040 units
24) What is the cost of carrying an inventory per unit per year? A. P1.00 B. P0.50 C. P2.00 D. P1.50
25) What is the average inventory? A. 740 B. 1,020 C. 500 D. 780
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started