Change to the Detail Gantt view with Schedule table and review the project critical path and tasks with free and total slack. Which task (ID)
- Change to the Detail Gantt view with Schedule table and review the project critical path and tasks with free and total slack. Which task (ID) has the most free slack? Which has the most total slack? How much is each slack?
Task Mode | Task Name | Start | Finish | Late Start | Late Finish | Critical | Free Slack | Total Slack |
Auto Scheduled | Exterior Finishes | Mon 23-08-14 | Fri 23-09-08 | Thu 23-08-17 | Wed 23-09-13 | No | 3 days | 3 days |
Auto Scheduled | Complete exterior brick | Mon 23-08-14 | Tue 23-09-05 | Thu 23-08-17 | Fri 23-09-08 | No | 0 days | 3 days |
Auto Scheduled | Complete exterior siding | Wed 23-09-06 | Fri 23-09-08 | Mon 23-09-11 | Wed 23-09-13 | No | 0 days | 3 days |
Auto Scheduled | Utility Rough-B97Ins and Complete Concrete | Mon 23-07-17 | Tue 23-08-15 | Wed 23-07-19 | Thu 23-09-28 | No | 2 days | 2 days |
Auto Scheduled | Rough-in plumbing | Fri 23-07-21 | Thu 23-07-27 | Wed 23-07-19 | Tue 23-07-25 | Yes | 0 days | -2 days |
Auto Scheduled | Conduct rough-in plumbing inspection | Fri 23-07-28 | Fri 23-07-28 | Thu 23-08-24 | Thu 23-08-24 | No | 0 days | 18 days |
Auto Scheduled | Place concrete for basement floor | Mon 23-07-31 | Tue 23-08-15 | Thu 23-09-14 | Thu 23-09-28 | No | 31 days | 31 days |
Auto Scheduled | Rough-in electrical | Fri 23-07-21 | Thu 23-07-27 | Thu 23-07-27 | Wed 23-08-02 | No | 0 days | 4 days |
Auto Scheduled | Conduct rough-in electrical inspection | Fri 23-07-28 | Fri 23-07-28 | Thu 23-08-03 | Thu 23-08-03 | No | 0 days | 4 days |
Auto Scheduled | Rough-in HVAC | Mon 23-07-31 | Wed 23-08-02 | Fri 23-08-04 | Wed 23-08-09 | No | 0 days | 4 days |
Auto Scheduled | Conduct rough-in HVAC inspection | Thu 23-08-03 | Thu 23-08-03 | Wed 23-09-06 | Wed 23-09-06 | No | 22 days | 22 days |
Auto Scheduled | Rough-in communication - phone, cable, computer, alarm | Mon 23-07-17 | Tue 23-07-18 | Tue 23-08-08 | Wed 23-08-09 | No | 15 days | 15 days |
Auto Scheduled | Interior Finishes | Mon 23-08-14 | Mon 23-09-25 | Thu 23-08-10 | Fri 23-10-13 | Yes | 0 days | -2 days |
Auto Scheduled | Insulation | Mon 23-08-14 | Tue 23-08-29 | Thu 23-08-10 | Thu 23-09-28 | Yes | 0 days | -2 days |
Auto Scheduled | Place wall insulation - 1st floor | Mon 23-08-14 | Mon 23-08-14 | Thu 23-08-10 | Thu 23-08-10 | Yes | 0 days | -2 days |
Auto Scheduled | Place wall insulation - 2nd floor | Tue 23-08-15 | Tue 23-08-15 | Tue 23-09-19 | Tue 23-09-19 | No | 3 days | 24 days |
Auto Scheduled | Place ceiling insulation - 2nd floor | Fri 23-08-25 | Fri 23-08-25 | Tue 23-09-26 | Tue 23-09-26 | No | 0 days | 21 days |
Auto Scheduled | Conduct insulation inspection | Mon 23-08-28 | Tue 23-08-29 | Wed 23-09-27 | Thu 23-09-28 | No | 21 days | 21 days |
Auto Scheduled | Drywall | Tue 23-08-15 | Fri 23-08-25 | Fri 23-08-11 | Fri 23-10-13 | Yes | 0 days | -2 days |
Auto Scheduled | Install drywall - 1st floor walls | Tue 23-08-15 | Wed 23-08-16 | Fri 23-08-11 | Mon 23-08-14 | Yes | 0 days | -2 days |
Auto Scheduled | Install drywall - 1st floor overhead | Thu 23-08-17 | Fri 23-08-18 | Tue 23-08-15 | Wed 23-08-16 | Yes | 0 days | -2 days |
Auto Scheduled | Install drywall 2nd floor walls | Mon 23-08-21 | Tue 23-08-22 | Wed 23-09-20 | Thu 23-09-21 | No | 0 days | 21 days |
Auto Scheduled | Install drywall 2nd floor overhead | Wed 23-08-23 | Thu 23-08-24 | Fri 23-09-22 | Mon 23-09-25 | No | 0 days | 21 days |
Auto Scheduled | Tape and float 1st floor drywall | Mon 23-08-21 | Mon 23-08-21 | Thu 23-08-17 | Thu 23-08-17 | Yes | 0 days | -2 days |
Auto Scheduled | Tape and float 2nd floor drywall | Fri 23-08-25 | Fri 23-08-25 | Fri 23-10-13 | Fri 23-10-13 | No | 33 days | 33 days |
Auto Scheduled | Paint and Wallpaper | Tue 23-08-22 | Thu 23-09-14 | Fri 23-08-18 | Fri 23-10-13 | Yes | 0 days | -2 days |
Auto Scheduled | Texture all except entry and kitchen - 1st floor | Tue 23-08-22 | Tue 23-08-22 | Fri 23-08-18 | Fri 23-08-18 | Yes | 0 days | -2 days |
Auto Scheduled | Paint all except entry and kitchen - 1st floor | Wed 23-08-23 | Wed 23-08-23 | Mon 23-08-21 | Mon 23-08-21 | Yes | 0 days | -2 days |
Auto Scheduled | Hang wallpaper entry and kitchen - 1st floor | Thu 23-08-24 | Thu 23-08-24 | Tue 23-08-22 | Tue 23-08-22 | Yes | 0 days | -2 days |
Auto Scheduled | Texture all - 2nd floor | Wed 23-08-23 | Wed 23-08-23 | Thu 23-10-12 | Thu 23-10-12 | No | 0 days | 34 days |
Auto Scheduled | Paint all - 2nd floor | Thu 23-08-24 | Thu 23-08-24 | Fri 23-10-13 | Fri 23-10-13 | No | 34 days | 34 days |
Auto Scheduled | Paint exterior siding & trim work | Mon 23-09-11 | Thu 23-09-14 | Thu 23-09-14 | Tue 23-09-19 | No | 0 days | 3 days |
Auto Scheduled | Cabinets | Fri 23-08-25 | Fri 23-09-01 | Wed 23-08-23 | Thu 23-09-28 | Yes | 0 days | -2 days |
Auto Scheduled | Install 1st floor - kitchen cabinets | Fri 23-08-25 | Mon 23-08-28 | Wed 23-08-23 | Thu 23-08-24 | Yes | 0 days | -2 days |
Auto Scheduled | Install 1st floor - master bath and guest cabinets | Tue 23-08-29 | Tue 23-08-29 | Fri 23-08-25 | Fri 23-08-25 | Yes | 0 days | -2 days |
Auto Scheduled | Install 2nd floor - hall bath and private bath cabinets | Wed 23-08-30 | Wed 23-08-30 | Tue 23-08-29 | Tue 23-08-29 | Yes | 0 days | -1 day |
Auto Scheduled | Install chair rails, crown moldings, trim | Thu 23-08-31 | Fri 23-09-01 | Wed 23-09-27 | Thu 23-09-28 | No | 18 days | 18 days |
Auto Scheduled | Finish Plumbing | Tue 23-08-29 | Wed 23-09-06 | Fri 23-08-25 | Fri 23-09-01 | Yes | 0 days | -2 days |
Auto Scheduled | Complete 1st floor - kitchen plumbing | Tue 23-08-29 | Tue 23-08-29 | Fri 23-08-25 | Fri 23-08-25 | Yes | 0 days | -2 days |
Auto Scheduled | Complete 1st floor - master bath and guest plumbing | Wed 23-08-30 | Thu 23-08-31 | Mon 23-08-28 | Tue 23-08-29 | Yes | 0 days | -2 days |
Auto Scheduled | Complete 2nd floor - hall bath and private bath plumbing | Fri 23-09-01 | Tue 23-09-05 | Wed 23-08-30 | Thu 23-08-31 | Yes | 0 days | -2 days |
Auto Scheduled | Conduct finish plumbing inspection | Wed 23-09-06 | Wed 23-09-06 | Fri 23-09-01 | Fri 23-09-01 | Yes | 0 days | -2 days |
Auto Scheduled | Finish Electrical | Wed 23-09-06 | Fri 23-09-08 | Tue 23-09-05 | Mon 23-09-11 | Yes | 0 days | -1 day |
Auto Scheduled | Complete 1st floor circuits to service panel | Wed 23-09-06 | Wed 23-09-06 | Thu 23-09-07 | Thu 23-09-07 | No | 0 days | 1 day |
Auto Scheduled | Complete 2nd floor circuits to service panel | Thu 23-09-07 | Thu 23-09-07 | Fri 23-09-08 | Fri 23-09-08 | No | 0 days | 1 day |
Auto Scheduled | Conduct finish electrical inspection | Fri 23-09-08 | Fri 23-09-08 | Mon 23-09-11 | Mon 23-09-11 | No | 1 day | 1 day |
Auto Scheduled | Complete communications wiring - phone, cable, computer, alarm | Thu 23-09-07 | Fri 23-09-08 | Tue 23-09-05 | Wed 23-09-06 | Yes | 0 days | -2 days |
Auto Scheduled | Finish HVAC | Mon 23-09-11 | Wed 23-09-13 | Thu 23-09-07 | Mon 23-09-11 | Yes | 0 days | -2 days |
Auto Scheduled | Complete 1st floor - zone 1 HVAC | Mon 23-09-11 | Mon 23-09-11 | Thu 23-09-07 | Thu 23-09-07 | Yes | 0 days | -2 days |
Auto Scheduled | Complete 2nd floor - zone 2 HVAC | Tue 23-09-12 | Tue 23-09-12 | Fri 23-09-08 | Fri 23-09-08 | Yes | 0 days | -2 days |
Auto Scheduled | Conduct HVAC inspection | Wed 23-09-13 | Wed 23-09-13 | Mon 23-09-11 | Mon 23-09-11 | Yes | 0 days | -2 days |
Auto Scheduled | Carpet, Tile and Appliances | Thu 23-09-14 | Mon 23-09-25 | Tue 23-09-12 | Thu 23-09-21 | Yes | 0 days | -2 days |
Auto Scheduled | Tile entry, kitchen and baths | Thu 23-09-14 | Mon 23-09-18 | Tue 23-09-12 | Thu 23-09-14 | Yes | 0 days | -2 days |
Auto Scheduled | Carpet 1st floor | Tue 23-09-19 | Wed 23-09-20 | Fri 23-09-15 | Mon 23-09-18 | Yes | 0 days | -2 days |
Auto Scheduled | Carpet 2nd floor | Thu 23-09-21 | Fri 23-09-22 | Tue 23-09-19 | Wed 23-09-20 | Yes | 0 days | -2 days |
Auto Scheduled | Install appliances | Mon 23-09-25 | Mon 23-09-25 | Thu 23-09-21 | Thu 23-09-21 | Yes | 0 days | -2 days |
Auto Scheduled | Landscaping and Grounds Work | Fri 23-09-15 | Mon 23-10-02 | Wed 23-09-20 | Thu 23-09-28 | Yes | 0 days | -2 days |
Auto Scheduled | Pour concrete driveway and sidewalks | Fri 23-09-15 | Mon 23-09-18 | Wed 23-09-20 | Thu 23-09-21 | No | 3 days | 3 days |
Auto Scheduled | Install backyard fence | Tue 23-09-26 | Wed 23-09-27 | Fri 23-09-22 | Mon 23-09-25 | Yes | 0 days | -2 days |
Auto Scheduled | Sod and complete plantings - front yard | Thu 23-09-28 | Fri 23-09-29 | Tue 23-09-26 | Wed 23-09-27 | Yes | 0 days | -2 days |
Auto Scheduled | Sod and complete plantings - backyard | Mon 23-10-02 | Mon 23-10-02 | Thu 23-09-28 | Thu 23-09-28 | Yes | 0 days | -2 days |
Auto Scheduled | Final Acceptance | Tue 23-10-03 | Fri 23-10-13 | Fri 23-09-29 | Wed 23-10-11 | Yes | 0 days | -2 days |
Auto Scheduled | Complete final inspection for certificate of occupancy | Tue 23-10-03 | Tue 23-10-03 | Fri 23-09-29 | Fri 23-09-29 | Yes | 0 days | -2 days |
Auto Scheduled | Cleanup for occupancy | Wed 23-10-04 | Wed 23-10-04 | Mon 23-10-02 | Mon 23-10-02 | Yes | 0 days | -2 days |
Auto Scheduled | Perform final walk-through inspection | Thu 23-10-05 | Thu 23-10-05 | Tue 23-10-03 | Tue 23-10-03 | Yes | 0 days | -2 days |
Auto Scheduled | Complete punch list items | Fri 23-10-06 | Fri 23-10-13 | Wed 23-10-04 | Wed 23-10-11 | Yes | 0 days | -2 days |
Auto Scheduled | Project Complete | Fri 23-10-13 | Fri 23-10-13 | Wed 23-10-11 | Wed 23-10-11 | Yes | 0 days | -2 days |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started