Complete the MRP record for a bicycle seat MRP Record Part Name: Seat Lead time =1 week On-hand =40 Safety stock =20 begin{tabular}{lcccccccc} Order quantity
Complete the MRP record for a bicycle seat
MRP Record Part Name: Seat Lead time =1 week On-hand =40 Safety stock =20 \begin{tabular}{lcccccccc} Order quantity & Week & Week & Week & Week & Week & Week & Week & Week \\ FOQ =100 & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 \\ \hline Gross requirements & 70 & 50 & 80 & 80 & 70 & 60 & 80 & 80 \end{tabular} Scheduled receipts Available inventory Net requirements Planned order receipts Planned order releasesStep by Step Solution