Complete this exercise in MSProject. Your project has three dedicated resources: HR Manager, costing $75/hour, HR Analyst, costing $25/hour, and Benefits Coordinator, costing $15/hour. Resource
Complete this exercise in MSProject.
Your project has three dedicated resources: HR Manager, costing $75/hour, HR Analyst, costing $25/hour, and Benefits Coordinator, costing $15/hour. Resource assignments are as shown:
Task | Predecessor | Duration | Resource |
A | - | 2 | HR Manager |
B | - | 7 | HR Analyst |
C | A | 4 | HR Analyst |
D | B, C | 8 | HR Analyst |
E | D | 8 | Benefits Coordinator |
F | D | 6 | Benefits Coordinator |
G | E | 3 | HR Analyst |
H | E, F | 6 | HR Manager |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started