Question
consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $3,900,000 investment in threading
consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $3,900,000 investment in threading equipment to get the project started; the project will last for three years. the accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $250 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 3-year project life. It also estimates a salvage value of $460,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $330 per ton. The engineering department estimates you will need an initial net working capital investment of $480,000. You require a return of 10 percent and face a marginal tax rate of 25 percent on this project. suppose you are confident about your own projections, but you are a little unsure about Detroits actual machine screw requirement.
a) what is the sensitivity of the project OCF to changes in the quantity supply. ( Do not round intermediate calculations and round your answer to two decimal place. b) what is the sensitivity of NPV to changes in quantity supplied. c)given the sensitivity number you calculated, is there some minimum level of output below which you wouldn't want to operate ?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started