Consider the following project ( times given in day: table [ [ Activity , a , m , b , Predecessors ] , [

Consider the following project (times given in day:
\table[[Activity,a,m,b,Predecessors],[A,1,4,7,--],[B,2,2,2,--],[C,2,5,8,A],[D,3,4,5,A],[E,4,6,8,C,B],[F,0,0,6,C,B],[G,3,6,9,D,E]]
Find:
The network.
2.All expected activity times, variances, and slacks
3.The critical path and expected completion time
The probability the project will be done in 23 days.
5.The completion time corresponding to 95% probability.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these General Management questions