Consider the following work breakdown structure: table [ [ , Time Estimates ( days ) ] , [ Activity , Precedes,Optimistic,Most Likely,Pessimistic ] ,

Consider the following work breakdown structure:
\table[[,Time Estimates (days)],[Activity,Precedes,Optimistic,Most Likely,Pessimistic],[Start,A,B,C,-,-,-],[A,D,38,50,62],[B,E,90,99,108],[C,End,85,100,115],[D,F,19,25,31],[E,End,91,100,115],[F,End,62,65,68]]
What is the estimated expected (mean) time for activity E?
Multiple Choice
91 days
99 days
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these General Management questions

Question

Which entry mode should the company use?

Answered: 1 week ago