Question
Consider the table below which includes time and activity data for a Small IT Project. All duration estimates or estimated times are in days. Perform
Consider the table below which includes time and activity data for a Small IT Project. All duration estimates or estimated times are in days. Perform a critical path analysis for this project.
Activity ID | Duration (days) | Predecessor |
A | 4 | - |
B | 3 | A |
C | 6 | B |
D | 5 | B |
E | 3 | C, D |
F | 7 | D |
G | 2 | E |
H | 9 | F, G |
Draw a network diagram representing the project. MS Powerpoint or Visio are good tools for this task. (10 points)
2. Identify and list all of the paths through the network diagram and note how long they are. (6 points) Ex: The project has the following 3 paths: Path 1 AEDG 5 days. Path 2 BDFHJ 7 days.
3. What is the critical path for this project? Explain your reasoning. (4 points)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started