Considering the following project data in the table. Assuming that in the baseline schedule every activity stars at the early start time (critical path method).

Considering the following project data in the table. Assuming that in the baseline schedule every activity stars at the early start time (critical path method). The actual progress and cost are recorded at the end of 15th week.

activity

Duration(week)

cost

completed

Actual cost

Immediate successors

1

4

10

100%

18

2,5

2

7

30

100%

26

3,4,7

3

2

36

100%

48

6

4

6

80

50%

60

6

5

3

46

100%

52

6

6

9

60

0%

0

8,10

7

3

20

10%

10

8,10

8

10

90

0%

0

9

9

9

72

0%

0

10

6

55

0%

0

  1. Give the cumulative planned value of each week.
  2. According to the actual progress and cost data, calculate the SV, SPI, CV, CPI , and explain the meaning of these indicators.
  3. According to the actual progress data, calculate the ES, SV(t), SPI(t), and explain the meaning of these indicators.

Step by Step Solution

3.56 Rating (146 Votes )

There are 3 Steps involved in it

Step: 1

a The following formula is used to calculate the cumulative planned value for each week b Cumulative ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions