Considering the following project, determine the Critical Path. Activity Expected Duration Predecessor A 5 - B 3 A C 1 A, B D 5 C
Considering the following project, determine the Critical Path.
Activity | Expected Duration | Predecessor |
A | 5 | - |
B | 3 | A |
C | 1 | A, B |
D | 5 | C |
E | 10 | B |
F | 2 | E |
G | 3 | D |
H | 4 | F, G |
I | 5 | H |
Notes:
- Durations are in days.
a. | A, B, E, F, H, I | |
b. | A, B, H, I | |
c. | A, B, C, D, G, H, I | |
d. | A, B, E, F, I |