Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Construction Risk Management Assignment using @Risk software Monte Carlo Stimulation. Your estimating and project team has been doing material take - offs and they, along

Construction Risk Management Assignment using @Risk software Monte Carlo Stimulation.
Your estimating and project team has been doing material take-offs and they, along with
King Constructions Vice President for Estimating, Joe Scarponi, have briefed you.
Their briefing is summarized below:
1. Project Approach: Our prospective project superintendent, Albert Jones summed
up the project approach: The way to tackle this project is for us to do the slab
demolition and to form and pour the replacement slabs. The client has a short
completion time on this project9 months, and we cannot afford delays since we
may already have some weather issues given the time of the year.
2. Concrete Slab Demolition: The team has estimated that the costs for the
demolition and removal of the concrete slabs as follows:
a. Material: For the demolition phase of the project, the material cost is
estimated to be $0.00.
b. Equipment: the equipment cost for the demolition is as follows: Albert
Jones says we need to complete the excavation in 120 days. He plans to
have one large excavator and front end loader feeding two 5CY dump
trucks. Each excavator can demolish an average of four slabs a day, but if
the crew and truck teams are not in synch, their productivity may drop to
two slab a day. Conversely, an experienced crew might be able to
demolish up to six slabs a day. Rental Cost on a Caterpillar EX-300
excavator with a jack hammer attachment is $5,000/week. Rental cost of
5 CY dump trucks is $1,500/week. Rental Cost on a Front End Loader is
$2,000/week. Scarponi estimates the demolition equipment cost as:
Minimum Equipment Cost: $390,000
Most Likely Equipment Cost: $480,000
Maximum Equipment Cost: $700,000
c. Labor: King Construction will have several foremen on the job, but will
hire most of the concrete finishers and laborers locally. The key variable
impacting the labor cost will be productivity. Scarponi estimates that a
a crew of 10 to 20 laborers will be needed to support the demolition and
debris removal, and recommends hiring 15 to start the project. He feels
that he can hire them in Pensacola, but will have to pay them the client
mandated Davis-Bacon wages.
Minimum Labor Cost: $150,000
Most Likely Labor Cost: $275,000
Maximum Labor Cost: $450,000
3. Concrete Slab Replacement:
2
a. Labor: Albert Jones recommends forming and pouring 4-8 slabs at a time,
in a checkerboard fashion across the parking apron. He believes this work
will require 50 to 75 laborers and concrete finishers. He estimates that
the labor to form the slabs as follows:
Average Crew: $1,450,000
Poor Crew: $1,775,000
Highly productive Crew: $1,150,000
b. Material: The team says that the volume of concrete in the slabs is easy
to estimate, but the issue is how much waste to include in the bid and how
much additional concrete will be required due to the sub base condition
underneath the slab. If the concrete crews are poor, the risk is some of the
concrete will set up before the slabs can be properly finished. In such
cases, the slabs must be removed and re-formed and re-poured. They
recommend that a wastage factor of no less than 5% be used with 10%
being most likely and 20% being worst case. The price of 3500 PSI
concrete in Pensacola is anticipated to be $110/CY, but could fluctuate
from $100/CY to $118/CY.
Lowest Estimated Concrete Cost: $3,080,000
Most Likely Concrete Cost: $3,225,000
Highest Estimated Concrete Cost: $3,500,000
4. Job Overhead: Jones and Scarponi are concerned that the quality of the crews
hired in Pensacola could cause the company to have to put more project foremen
and field superintendents on the project to oversee both self-performed but also
subcontracted work. They wont know for sure until they hire the personnel once
they begin to mobilize. Scarponi estimates the job overhead at $275,000 but it
could go as high as $400,000. Lowest estimated cost for job overhead is
$200,000.
Model this problem in Excel and use @Risk (Excel Add-in) simulation to prepare
your best estimate. After that answer the following questions:
1. What will be the most likely cost of this project with 90% confidence?
2. Compare this cost with your earlier estimate (without using @Risk) and
discuss your findings?
3. If your bid price is $6.0M, would you complete this project in profit/loss?
Provide all relevant graphs and data (copy and attach graph from @Risk excel
spreadsheet). PLEASE ENSURE THAT YOUR EXCEL FILE SHOULD BE
CONVERTED TO PDF FILE WHEN YOU SUBMIT YOUR ANSWERS. Use
Triangular distribution.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Wildlife Ecology Conservation And Management

Authors: Anthony R. E. Sinclair, John M. Fryxell, Graeme Caughley

2nd Edition

1405107375, 978-1405107372

More Books

Students also viewed these General Management questions

Question

Are the investments going to be supported by the stakeholders?

Answered: 1 week ago