ControlThree critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. Activity NT CT CC NC Predecessor

ControlThree critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.
Activity NT CT CC NC Predecessor
A 7 days 5 days $9000 $7000
B 8 days 6 days $8000 $6000
C 3 days 2 days $2400 $1800 A
D 12 days 9 days $7700 $5000 B
a. What is the project length?
[ Select ]
b. What is the critical path?
[ Select ]
c. To reduce the project by one day, which activity would be crashed and how much would it cost?
[ Select ]
d. If we wanted to crash the project by an additional day, which activity would be crashed and how much would the total cost be for the two days?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management An Introduction

Authors: David Boddy

6th Edition

129200424X, 978-1292004242

More Books

Students also viewed these General Management questions