Coronado Industries manufactures a product with a standard direct labor cost of two hours at $18 per hour. During July, 1400 units were produced using
Coronado Industries manufactures a product with a standard direct labor cost of two hours at $18 per hour. During July, 1400 units were produced using 3200 hours at $18.30 per hour. The labor price variance was $960 U. O $8160 F. O $8160 U. O $7200 U