Question

1 Approved Answer

Cost Analysis You are estimating the cost of a personnel shelter and you have collected cost data on 10 shelters. The mean cost was $18,549.

Cost Analysis

You are estimating the cost of a personnel shelter and you have collected cost data on 10 shelters. The mean cost was $18,549. The median cost is $19,106. There is a range in the cost of $10,055. The variance is $130,321. The standard deviation is $3,610. If you use the average cost of the shelters as your estimate, then, on average:

A. You could expect to be off by 7.03 %.

B. You could expect to be off by $1,854.90.

C. You could expect to be off by 19.46%.

D. You could expect to be off by $10,055.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Comparative international accounting

Authors: Christopher nobes, Robert parker

9th Edition

273703579, 978-0273703570

More Books

Students also viewed these Accounting questions

Question

98. For a compound random variable S = N i=1 Xi , find Cov(N, S).

Answered: 1 week ago