course is work study and ergonomics A continuous stop watch time study was conducted on a shaping operation that consists of 5 elements as shown

course is work study and ergonomics image text in transcribed
A continuous stop watch time study was conducted on a shaping operation that consists of 5 elements as shown in the table below. Note: Au reaaings in the tabie above are in munutes. Q1- Assuming 3\% personal and fatigue allowances and 2% Delay allowances, find the standard time to produce one unit? Q2- How many units can be produced per week, assuming 8 hours of work/day and 5 working days per week? Q3- Calculate the required number of observations for the first, second and the last element (i.e. for load machine, Run and Material handling clements)? Use 10 percent precision. Hint: N1=(i=1Nxis20Nj=1nxi,2(i=1Nxwi)2)2 for i =1,2,5

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Encompassing The Future Offshore Oil And Gas Operations Environment Health And Safety Performance Management Policy Economics Law And Environment

Authors: William J. Cairns; Ann G Wilkie; Judith Hackitt; Peter Hepburn; Ewan MacAngus; Rita Marcella; Hayley

1st Edition

1999766210, 9781999766214

More Books

Students also viewed these General Management questions

Question

=+1. Why did the centralization of decisions in Wal-Marts

Answered: 1 week ago

Question

Why adaptation is necessary

Answered: 1 week ago