Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Crash the following project by at least 5 days using the contractor and report the crash cost per day. We don't want you to optimise

image text in transcribed

Crash the following project by at least 5 days using the contractor and report the crash cost per day. We don't want you to optimise the crash let the contractor do half of the work of the task(s) you choose to crash.) Resource Name Max. Units Std. Rate Developer 100% $66/hr Senior Admin 100% $116/hr Admin 100% $66/hr Designer 100% $116/hr Contractor 100% $159/hr ID Task Name 1 Project started 2 Design module 4 days 3 Code module Duration Predecessors Resource Names Type 0 days Fixed Units 1 Designer Fixed Units 25 days 2 Developer Fixed Work 5 days 1 Senior Admin Fixed Work 4 days Admin Fixed Units 0 days 3,5 Fixed Units 4 Prepare server 5 Install server 4 6 Project completed Answer: X Crash the following project by at least 5 days using the contractor and report the crash cost per day. We don't want you to optimise the crash let the contractor do half of the work of the task(s) you choose to crash.) Resource Name Max. Units Std. Rate Developer 100% $66/hr Senior Admin 100% $116/hr Admin 100% $66/hr Designer 100% $116/hr Contractor 100% $159/hr ID Task Name 1 Project started 2 Design module 4 days 3 Code module Duration Predecessors Resource Names Type 0 days Fixed Units 1 Designer Fixed Units 25 days 2 Developer Fixed Work 5 days 1 Senior Admin Fixed Work 4 days Admin Fixed Units 0 days 3,5 Fixed Units 4 Prepare server 5 Install server 4 6 Project completed Answer: X

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Internal Auditing Pocket Guide

Authors: J. P. Russell

1st Edition

0873895606, 978-0873895606

More Books

Students also viewed these Accounting questions

Question

8. Explain the difference between translation and interpretation.

Answered: 1 week ago

Question

10. Discuss the complexities of language policies.

Answered: 1 week ago

Question

1. Understand how verbal and nonverbal communication differ.

Answered: 1 week ago