Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Create Project Schedule in MGG software, simple Gantt chart. Project should contain four phases: Initiating Phase, Planning Phase, Executing Phase, Closing Phase. Each of the

Create Project Schedule in MGG software, simple Gantt chart. Project should contain four phases: Initiating Phase, Planning Phase, Executing Phase, Closing Phase. Each of the Work Packages from your WBS should be placed into the appropriate Phase in your MSG Project Schedule.

  • Planning to embark on a solo trip around the world.
  • This trip must conform to the following constraints:
    • Have a total duration of 20 weeks.
    • The budget for the trip is $20,000.
    • You must visit a minimum of 10 countries on three continents
    • Mode of travel must contain at least:
      • two flights
      • one ferry/cruise
      • one train
      • one rental car
      • one bus
    • Project start date 15 September 2023.
  • Include at least three levels, i.e., the Project plus two additional levels.
  • Include at least 15 work packages.
  • Contains 100% of the scope of the project.

. For each Work Package, define the Activities needed to complete the Work Package. For each Activity, define the:

  • Assigned to Jasvir Singh
  • Duration
  • Progress
  • Start Date information as follows:
    • For those activities that should start on a specific date, directly enter this date into the Start Date field
    • For those activities that are dependent on the completion of prior activities, enter the dependency formula into the Start Date field
  • At least 50% of activities must use dependency formulas
  • Consider your project to have progressed one month from the Schedule Start. Update the Progress field for the various activities that should either be complete (100%) or started (less than 100%)
  • Define at least eight (8) milestones and add them to your Project Schedule

Detailed Budget.

The following should be performed:

  • Your Detailed Budget should include all costs for the project (e.g. flights, accommodations, etc.).
  • The time periods should be monthly (i.e. each column represents a month)
  • Each Activity from the Project Schedule that resulted in a project cost should be listed in the Detailed Budget and the cost should be placed under the appropriate month(s).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

11th Edition

978-0324651812, 324651813, 978-0324651751

More Books

Students also viewed these General Management questions

Question

6. Do you currently have a team agreement?

Answered: 1 week ago