Creger Corporation, which makes landing gears, has provided the following data for a recent month: Budgeted production 7,900 gears Standard machine-hours per gear 9.3 machine-hours
Creger Corporation, which makes landing gears, has provided the following data for a recent month:
Budgeted production | 7,900 | gears |
---|---|---|
Standard machine-hours per gear | 9.3 | machine-hours |
Budgeted supplies cost | $ 6.20 | per machine-hour |
Actual production | 8,300 | gears |
Actual machine-hours | 76,930 | machine-hours |
Actual supplies cost (total) | $479,438 |
Required:
Determine the rate and efficiency variances for the variable overhead item supplies and indicate whether those variances are favorable or unfavorable.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started