CRX Industries Inc. manufactures a lid for a hydroponic garden planter. The standard cost for one planter is as follows: Std. Quality of Hours Standard
CRX Industries Inc. manufactures a lid for a hydroponic garden planter. The standard cost for one planter is as follows:
Std. Quality of Hours | Standard Price or Rate | Standard Cost | |
Direct Materials | 2.2 kgs | $6.50 | $14.30 |
Direct Labour | .45 hours | $9.00 | $4.05 |
Variable Mfg. Overhead | .20 machine hours | $2.50 per machine hour | $0.50 |
Total Std. Cost | $18.85 |
The plant has been experiencing problems for some time, as is shown by its June income statement when it made and sold 15,000 planters; the normal volume is 15,150 planters per month. Fixed costs are allocated using machine-hours.
Flexible Budget | Actual | |
Sales (15,000 planters) | $750,000 | $750,000 |
Less: Variable Expenses: | ||
Variable COGS* | $282,750 | $305,000 |
Variable Selling Exp. | $ 25,000 | $ 25,000 |
Total Variable Expenses | $307,750 | $330,000 |
Contribution Margin | $442,500 | $420,000 |
Less: Fixed Expenses: | ||
Mfg. Overhead | $260,580 | $260,5680 |
Selling and Admin | $105,000 | $105,000 |
Total Fixed Expenses | $366,580 | $366,580 |
Net Income | $75,920 | $53,420 |
* Includes direct materials, labour and variable mfg. overhead |
Joe Bidenold, the general manager of the Plant, wants to get things under control. He needs information about the operations in June since the income statement signaled that the problem could be due to the variable cost of goods sold. Bidenold learns the following about operations and costs in June:
- 50,000 kilograms of materials were purchased at a cost of $6.25 per kilogram.
- 34,600 kilograms of materials were used in production. (Finished goods and work-in-process inventories are insignificant and can be ignored.)
- 14,800 direct labour-hours were worked at a cost of $10 per hour.
- Variable manufacturing overhead cost totaling $28,290 for the month was incurred. A total of 7,900 machine hours was recorded.
It is the company's policy to close all variances to cost of goods sold on a monthly basis.
Required:
1. Calculate the following variances for june
- Direct materials price and quantity variances.
- Direct labour rate and efficiency variances. Is Joe Bidenold correct in his assumption, please explain, if not why?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started