D . PMO Q 1 8 . During project execution, the client provided updated requirement, which will only require a minor adjustment to the work

D. PMO
Q18. During project execution, the client provided updated requirement, which will only require a minor adjustment to the work breakdown structure. What should you do first?
A. Submit a change request to update the scope baseline.
B. Submit a change request t update the schedule baseline.
C. Adjust the WBS because the change is minor.
D. Deny the request because it represents scope creep.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Big Data In Just 7 Chapters

Authors: Prof Marcus Vinicius Pinto

1st Edition

B09NZ7ZX72, 979-8787954036

More Books

Students also viewed these Databases questions

Question

5. Give examples of binary thinking.

Answered: 1 week ago