Question

1 Approved Answer

Data are for 6 different weeks ( not cumulative ) You monitored figures on cost and planned / earned value for each individual project week

Data are for 6 different weeks (not cumulative) You monitored figures on cost and planned/earned value for each individual project week until the data date at the end of the sixth week. What is the status of this project at this date?
Project Week
Actual Costs
Earned Value
Planned Value
1
$75,000
$61,000
$57,000
2
$95,000
$79,000
$69,000
3
$130,000
$152,000
$160,000
4
$54,000
$74,000
$71,000
5
$205,000
$203,000
$209,000
6
$45,000
$50,000
$71,000
a)
The project is ahead of schedule and over budget
Incorrect Response
b)
The project is behind schedule and over budget
c)
The project is ahead of schedule and under budget
Correct Answer
d)
The project is behind schedule and under budget

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Project Management

Authors: Joseph Heagney

5th Edition

0814437362, 978-0814437360

More Books

Students also viewed these General Management questions

Question

Th eir solution was to give me a long-distance number to call.

Answered: 1 week ago