Define Critical path, Slack time, Resource Levelling and Dummy activity with reference to PERT and CPM . An architect has been awarded a contract to
Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with reference to PERT and CPM
An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.
Job
Description
Predecessor
Expected time in days
A
Prepare preliminary sketches
NA
B
Outline specifications
NA
C
Prepare drawings
A
D
Write specifications
A B
E
Run prints
C D
F
Have specifications printed
B D
G
Assemble bid package
E F
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started