Define Critical path, Slack time, Resource Levelling and Dummy activity with reference to PERT and CPM . An architect has been awarded a contract to

Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with reference to PERT and CPM.
An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.
Job
Description
Predecessor
Expected time in days
A
Prepare preliminary sketches
NA
2
B
Outline specifications
NA
1
C
Prepare drawings
A
3
D
Write specifications
A B
2
E
Run prints
C D
1
F
Have specifications printed
B D
3
G
Assemble bid package
E F
1

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Chuck Williams

4th Edition

978-0324316797, 0324316798

More Books

Students also viewed these General Management questions