Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year:
Activity | Expected Cost | Activity Driver | Activity Capacity | |||
Setting up equipment | $480,000 | Number of setups | 600 | |||
Ordering costs | 360,000 | Number of orders | 18,000 | |||
Machine costs | 840,000 | Machine hours | 42,000 | |||
Receiving | 400,000 | Receiving hours | 10,000 |
Deoro produces two models of dishwashers with the following expected prime costs and activity demands:
Model A | Model B | ||||
Direct materials | $600,000 | $800,000 | |||
Direct labor | 480,000 | 480,000 | |||
Units completed | 16,000 | 8,000 | |||
Direct labor hours | 6,000 | 2,000 | |||
Number of setups | 400 | 200 | |||
Number of orders | 6,000 | 12,000 | |||
Machine hours | 24,000 | 18,000 | |||
Receiving hours | 3,000 | 7,000 |
The company's normal activity is 8,000 direct labor hours.
Required:
1. Determine the unit cost for each model using direct labor hours to apply overhead.
Unit Cost | |
Model A | $fill in the blank 1 |
Model B | $fill in the blank 2 |
2. Determine the unit cost for each model using the four activity drivers. Round your answers to nearest cent.
Unit Cost | |
Model A | $fill in the blank 3 |
Model B | $fill in the blank 4 |
3. Which method produces the more accurate cost assignment?
Direct labor hoursFour activity drivers
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started