Question

1 Approved Answer

Development of Version 2 . 0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities

Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:
Activity
Normal Time(weeks)
Crash Time(weeks)
Normal Cost
Crashing Cost
Immediate Predecessor(s)
A
4
3
$ 2 comma 100
$ 2 comma 700
long dash
B
2
1
$ 2 comma 200
$ 2 comma 800
long dash
C
3
3
$ 600
$ 600
long dash
D
8
4
$ 2 comma 500
$ 2 comma 780
A
E
6
3
$ 1 comma 000
$ 1 comma 375
B
F
3
2
$ 3 comma 000
$ 4 comma 200
C
G
4
2
$ 1 comma 500
$ 2 comma 100
D, E
Part 2
a) What is the project completion date?
Based on the given information regarding the activities for the project, the project length=
16 weeks.
Part 3
b) What is the total cost required for completing this project on normal time?
The total cost required for completing this project on normal time=$
12,900.
Part 4
c) If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions