Question

1 Approved Answer

Development of Version 2 . 0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities

Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:
Activity
Normal Time(weeks)
Crash Time(weeks)
Normal Cost
Total Cost with Crashing
Immediate Predecessor(s)
A
44
33
$ 2 comma 100$2,100
$ 2 comma 750$2,750
long dash
B
22
11
$ 2 comma 300$2,300
$ 2 comma 900$2,900
long dash
C
33
33
$ 500$500
$ 500$500
long dash
D
88
44
$ 2 comma 500$2,500
$ 2 comma 800$2,800
A
E
66
33
$ 1 comma 000$1,000
$ 1 comma 450$1,450
B
F
33
22
$ 3 comma 200$3,200
$ 4 comma 700$4,700
C
G
44
22
$ 1 comma 400$1,400
$ 1 comma 900$1,900
D, E
Part 2
a) Based on the given information regarding the activities for the project, the project length= enter your response here weeks.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel Jr.

8th edition

470533021, 978-0470533024

More Books

Students also viewed these General Management questions

Question

How have you handled a difficult situation with people

Answered: 1 week ago