Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct

Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis

Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 70,000 units of product were as follows:

Standard Costs Actual Costs
Direct materials 231,000 lbs. at $5.50 228,700 lbs. at $5.40
Direct labor 17,500 hrs. at $16.10 17,900 hrs. at $16.30
Factory overhead Rates per direct labor hr.,
based on 100% of normal
capacity of 18,260 direct
labor hrs.:
Variable cost, $3.10 $53,710 variable cost
Fixed cost, $4.90 $89,474 fixed cost

Each unit requires 0.25 hour of direct labor.

Required:

a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Direct Materials Price Variance $ Favorable
Direct Materials Quantity Variance $ Favorable
Total Direct Materials Cost Variance $ Favorable

b. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Direct Labor Rate Variance $ Unfavorable
Direct Labor Time Variance $ Unfavorable
Total Direct Labor Cost Variance $ Unfavorable

c. Determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Variable factory overhead controllable variance $ Favorable
Fixed factory overhead volume variance $ Unfavorable
Total factory overhead cost variance $ Unfavorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Development Of Accounting And Auditing Systems In China

Authors: Xu-Dong Ji

1st Edition

0415792886, 978-0415792882

More Books

Students also viewed these Accounting questions