Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct
Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis
Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 78,000 units of product were as follows:
Standard Costs | Actual Costs | ||
Direct materials | 241,800 lbs. at $5.60 | 239,400 lbs. at $5.40 | |
Direct labor | 19,500 hrs. at $18.20 | 19,950 hrs. at $18.60 | |
Factory overhead | Rates per direct labor hr., | ||
based on 100% of normal | |||
capacity of 20,350 direct | |||
labor hrs.: | |||
Variable cost, $4.20 | $81,080 variable cost | ||
Fixed cost, $6.60 | $134,310 fixed cost |
Each unit requires 0.25 hour of direct labor.
Required:
a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Direct Materials Price Variance | $fill in the blank 1 | |
Direct Materials Quantity Variance | $fill in the blank 3 | |
Total Direct Materials Cost Variance | $fill in the blank 5 |
b. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Direct Labor Rate Variance | $fill in the blank 7 | |
Direct Labor Time Variance | $fill in the blank 9 | |
Total Direct Labor Cost Variance | $fill in the blank 11 |
c. Determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Variable factory overhead controllable variance | $fill in the blank 13 | |
Fixed factory overhead volume variance | $fill in the blank 15 | |
Total factory overhead cost variance | $fill in the blank 17 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started