Question
Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct
Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis
Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 40,000 units of product were as follows:
Standard Costs | Actual Costs | ||
Direct materials | 120,000 lb. at $3.20 | 118,500 lb. at $3.25 | |
Direct labor | 12,000 hrs. at $24.40 | 11,700 hrs. at $25.00 | |
Factory overhead | Rates per direct labor hr., | ||
based on 100% of normal | |||
capacity of 15,000 direct | |||
labor hrs.: | |||
Variable cost, $8.00 | $91,200 variable cost | ||
Fixed cost, $10.00 | $150,000 fixed cost |
Each unit requires 0.3 hour of direct labor.
Required:
a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Direct materials price variance | $fill in the blank 1 |
|
Direct materials quantity variance | fill in the blank 3 |
|
Total direct materials cost variance | $fill in the blank 5 |
|
b. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Direct labor rate variance | $fill in the blank 7 |
|
Direct labor time variance | fill in the blank 9 |
|
Total direct labor cost variance | $fill in the blank 11 |
|
c. Determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Variable factory overhead controllable variance | $fill in the blank 13 |
|
Fixed factory overhead volume variance | fill in the blank 15 |
|
Total factory overhead cost variance | $fill in the blank 17 |
|
fill in the blanks pls ;)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started