Question
Direct Materials Under normal conditions, Sarah spends $8.40 per unit of materials, and it will take 3.60 units of material per pair of shoes. During
Direct Materials
Under normal conditions, Sarah spends $8.40 per unit of materials, and it will take 3.60 units of material per pair of shoes. During July, Sole Purpose Shoe Company incurred actual direct materials costs of $62,211 for 6,990 units of direct materials in the production of 2,175 pairs of shoes.
Complete the following table, showing the direct materials variance relationships for July for Sole Purpose Shoe Company. If required, round your answers to two decimal places. When entering variances, use a negative number for a favorable cost variance, and a positive number for an unfavorable cost variance.
Actual Cost | Standard Cost | |||||||||
Actual Quantity | X | Actual Price | Actual Quantity | X | Standard Price | Standard Quantity | X | Standard Price | ||
fill in the blank dd9212043036ffa_1 | X | $fill in the blank dd9212043036ffa_2 | fill in the blank dd9212043036ffa_3 | X | $fill in the blank dd9212043036ffa_4 | fill in the blank dd9212043036ffa_5 | X | $fill in the blank dd9212043036ffa_6 | ||
= $fill in the blank dd9212043036ffa_7 | = $fill in the blank dd9212043036ffa_8 | = $fill in the blank dd9212043036ffa_9 | ||||||||
UnfavorableFavorableUnfavorable Direct MaterialsCostPriceQuantityRateTimePrice Variance: | UnfavorableFavorableFavorable Direct MaterialsCostPriceQuantityRateTimeQuantity Variance: | |||||||||
$fill in the blank dd9212043036ffa_14 | $fill in the blank dd9212043036ffa_15 | |||||||||
UnfavorableFavorableFavorable Total Direct MaterialsCostPriceQuantityRateTimeCost Variance: | ||||||||||
$fill in the blank dd9212043036ffa_18 |
Direct Labor
Under normal conditions, Sarah pays her employees $8.50 per hour, and it will take 2.80 hours of labor per pair of shoes. During August, Sole Purpose Shoe Company incurred actual direct labor costs of $65,340 for 7,260 hours of direct labor in the production of 2,200 pairs of shoes.
Complete the following table, showing the direct labor variance relationships for August for Sole Purpose Shoe Company. If required, round your answers to two decimal places. When entering variances, use a negative number for a favorable variance, and a positive number for an unfavorable variance.
Actual Cost | Standard Cost | |||||||||
Actual Hours | X | Actual Rate | Actual Hours | X | Standard Rate | Standard Hours | X | Standard Rate | ||
fill in the blank ea9e5bf89fa501b_1 | X | $fill in the blank ea9e5bf89fa501b_2 | fill in the blank ea9e5bf89fa501b_3 | X | $fill in the blank ea9e5bf89fa501b_4 | fill in the blank ea9e5bf89fa501b_5 | X | $fill in the blank ea9e5bf89fa501b_6 | ||
= $fill in the blank ea9e5bf89fa501b_7 | = $fill in the blank ea9e5bf89fa501b_8 | = $fill in the blank ea9e5bf89fa501b_9 | ||||||||
UnfavorableFavorableUnfavorable Direct LaborCostPriceQuantityRateTimeRate Variance: | UnfavorableFavorableUnfavorable Direct LaborCostPriceQuantityRateTimeTime Variance: | |||||||||
$fill in the blank ea9e5bf89fa501b_14 | $fill in the blank ea9e5bf89fa501b_15 | |||||||||
UnfavorableFavorableUnfavorable Total Direct LaborCostPriceQuantityRateTimeCost Variance: | ||||||||||
$fill in the blank ea9e5bf89fa501b_18 |
Budget Performance Report
Sarah has learned a lot from you over the past two months, and has compiled the following data for Sole Purpose Shoe Company for September using the techniques you taught her. She would like your help in preparing a Budget Performance Report for September. The company produced 3,500 pairs of shoes that required 12,250 units of material purchased at $8.20 per unit and 9,450 hours of labor at an hourly rate of $8.90 per hour during the month. Actual factory overhead during September was $28,350. When entering variances, use a negative number for a favorable cost variance, and a positive number for an unfavorable cost variance.
Use the data in the following table to prepare the Budget Performance Report for Sole Purpose Shoe Company for September.
Manufacturing Costs | Standard Price | Standard Quantity | Standard Cost Per Unit |
Direct materials | $8.40 per unit | 3.60 units per pair | $30.24 |
Direct labor | $8.50 per hour | 2.80 hours per pair | 23.80 |
Factory overhead | $2.70 per hour | 2.80 hours per pair | 7.56 |
Total standard cost per pair | $61.60 |
Sole Purpose Shoe Company Budget Performance Report For the Month Ended September 30 | |||
Manufacturing Costs | Actual Costs | Standard Cost at Actual Volume | Cost Variance - (Favorable) Unfavorable |
Direct materials | $fill in the blank f1e150f7f007076_1 | $fill in the blank f1e150f7f007076_2 | $fill in the blank f1e150f7f007076_3 |
Direct labor | fill in the blank f1e150f7f007076_4 | fill in the blank f1e150f7f007076_5 | fill in the blank f1e150f7f007076_6 |
Factory overhead | fill in the blank f1e150f7f007076_7 | fill in the blank f1e150f7f007076_8 | fill in the blank f1e150f7f007076_9 |
Total manufacturing costs | $fill in the blank f1e150f7f007076_10 | $fill in the blank f1e150f7f007076_11 | $fill in the blank f1e150f7f007076_12 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started