Question

1 Approved Answer

Direct Materials Under normal conditions, Sarah spends $8.40 per unit of materials, and it will take 3.60 units of material per pair of shoes. During

Direct Materials

Under normal conditions, Sarah spends $8.40 per unit of materials, and it will take 3.60 units of material per pair of shoes. During July, Sole Purpose Shoe Company incurred actual direct materials costs of $62,211 for 6,990 units of direct materials in the production of 2,175 pairs of shoes.

Complete the following table, showing the direct materials variance relationships for July for Sole Purpose Shoe Company. If required, round your answers to two decimal places. When entering variances, use a negative number for a favorable cost variance, and a positive number for an unfavorable cost variance.

Actual Cost Standard Cost
Actual Quantity X Actual Price Actual Quantity X Standard Price Standard Quantity X Standard Price
fill in the blank dd9212043036ffa_1 X $fill in the blank dd9212043036ffa_2 fill in the blank dd9212043036ffa_3 X $fill in the blank dd9212043036ffa_4 fill in the blank dd9212043036ffa_5 X $fill in the blank dd9212043036ffa_6
= $fill in the blank dd9212043036ffa_7 = $fill in the blank dd9212043036ffa_8 = $fill in the blank dd9212043036ffa_9

UnfavorableFavorableUnfavorable

Direct Materials

CostPriceQuantityRateTimePrice

Variance:

UnfavorableFavorableFavorable

Direct Materials

CostPriceQuantityRateTimeQuantity

Variance:
$fill in the blank dd9212043036ffa_14 $fill in the blank dd9212043036ffa_15

UnfavorableFavorableFavorable

Total Direct Materials

CostPriceQuantityRateTimeCost

Variance:
$fill in the blank dd9212043036ffa_18

Direct Labor

Under normal conditions, Sarah pays her employees $8.50 per hour, and it will take 2.80 hours of labor per pair of shoes. During August, Sole Purpose Shoe Company incurred actual direct labor costs of $65,340 for 7,260 hours of direct labor in the production of 2,200 pairs of shoes.

Complete the following table, showing the direct labor variance relationships for August for Sole Purpose Shoe Company. If required, round your answers to two decimal places. When entering variances, use a negative number for a favorable variance, and a positive number for an unfavorable variance.

Actual Cost Standard Cost
Actual Hours X Actual Rate Actual Hours X Standard Rate Standard Hours X Standard Rate
fill in the blank ea9e5bf89fa501b_1 X $fill in the blank ea9e5bf89fa501b_2 fill in the blank ea9e5bf89fa501b_3 X $fill in the blank ea9e5bf89fa501b_4 fill in the blank ea9e5bf89fa501b_5 X $fill in the blank ea9e5bf89fa501b_6
= $fill in the blank ea9e5bf89fa501b_7 = $fill in the blank ea9e5bf89fa501b_8 = $fill in the blank ea9e5bf89fa501b_9

UnfavorableFavorableUnfavorable

Direct Labor

CostPriceQuantityRateTimeRate

Variance:

UnfavorableFavorableUnfavorable

Direct Labor

CostPriceQuantityRateTimeTime

Variance:
$fill in the blank ea9e5bf89fa501b_14 $fill in the blank ea9e5bf89fa501b_15

UnfavorableFavorableUnfavorable

Total Direct Labor

CostPriceQuantityRateTimeCost

Variance:
$fill in the blank ea9e5bf89fa501b_18

Budget Performance Report

Sarah has learned a lot from you over the past two months, and has compiled the following data for Sole Purpose Shoe Company for September using the techniques you taught her. She would like your help in preparing a Budget Performance Report for September. The company produced 3,500 pairs of shoes that required 12,250 units of material purchased at $8.20 per unit and 9,450 hours of labor at an hourly rate of $8.90 per hour during the month. Actual factory overhead during September was $28,350. When entering variances, use a negative number for a favorable cost variance, and a positive number for an unfavorable cost variance.

Use the data in the following table to prepare the Budget Performance Report for Sole Purpose Shoe Company for September.

Manufacturing Costs Standard Price Standard Quantity Standard Cost Per Unit
Direct materials $8.40 per unit 3.60 units per pair $30.24
Direct labor $8.50 per hour 2.80 hours per pair 23.80
Factory overhead $2.70 per hour 2.80 hours per pair 7.56
Total standard cost per pair $61.60

Sole Purpose Shoe Company Budget Performance Report For the Month Ended September 30
Manufacturing Costs Actual Costs Standard Cost at Actual Volume Cost Variance - (Favorable) Unfavorable
Direct materials $fill in the blank f1e150f7f007076_1 $fill in the blank f1e150f7f007076_2 $fill in the blank f1e150f7f007076_3
Direct labor fill in the blank f1e150f7f007076_4 fill in the blank f1e150f7f007076_5 fill in the blank f1e150f7f007076_6
Factory overhead fill in the blank f1e150f7f007076_7 fill in the blank f1e150f7f007076_8 fill in the blank f1e150f7f007076_9
Total manufacturing costs $fill in the blank f1e150f7f007076_10 $fill in the blank f1e150f7f007076_11 $fill in the blank f1e150f7f007076_12

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advances In Quantitative Analysis Of Finance And Accounting (Vol. 5)

Authors: Lee Cheng Few

1st Edition

9812706283, 9789812706287

More Books

Students also viewed these Accounting questions

Question

=+a) Which will be smoother, a 50-day or a 200-day moving average?

Answered: 1 week ago

Question

What is your view of spirituality in the workplace?

Answered: 1 week ago