Question

1 Approved Answer

Dog Up ! Franks is looking at a new sausage system with an installed cost of $ 2 7 3 , 0 0 0 .

Dog Up! Franks is looking at a new sausage system with an installed cost of $273,000. This cost will be depreciated straight-line to zero over the project's 4-year life, at the end of which the sausage system can be scrapped for $42,000. The sausage system will save the firm $84,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $19,600.
If the tax rate is 21 percent and the discount rate is 9 percent, what is the NPV of this project?
Multiple Choice
$6,211.78
$6,522.37
$-17,293.77
$-11,578.90
$11,926.64

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Company Valuation Playbook Invest With Confidence

Authors: Charles Sunnucks

1st Edition

1838470816, 978-1838470814

More Books

Students also viewed these Finance questions