Doug Casey is in charge of planning andcoordinating next spring's sales management training program for his company. Doug listed the following activity information for this
Doug Casey is in charge of planning andcoordinating next spring's sales management training program for his company. Doug listed the following activity information for this project:
Time (weeks) Immediate Activity Description Predecessor Optimistic Most Probably Pessimistic A Plan Topic - 1.5 2.0 2.5 B Obtain Speakers A 2.0 2.5 6.0 C List meeting locations - 1.0 2.0 3.0 D Select location C 1.5 2.0 2.5 E Finalize speaker travel plans B,D 0.5 1.0 1.5 F Make final check with speakers E 1.0 2.0 3.0 G Prepare and mail brochure B,D 3.0 3.5 7.0 H Take reservations G 3.0 4.0 5.0 I Handle last-minute details F,H 1.5 2.0 2.5 a. Draw a project network b. Prepare an activity schedule c. What are the critical activities and what is the expected project completion time?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started