Question
1 Approved Answer
Draw PERT Chart with earliest and latest start and finish times/activity. Fill in the slack time in the table for each activity. Show the slack
- Draw PERT Chart with earliest and latest start and finish times/activity. Fill in the slack time in the table for each activity. Show the slack time for each path for all paths and show Critical Path (CPM) and CPM time.
- What is the expected time for 68, 95 and 99 percent Confidence Interval (CI) for the project?
- Show the 75%,
\begin{tabular}{|c|c|c|c|c|c|c|c|} \hline ID 7 & Preceding & Start & End & Activity & Staff & Optimisfic & Pessimistic \\ Activity & Activity & Node & Node & Time & Requised & Time & Time \\ \hline A & - & S & 1 & 3 & 4 & 2 & 4 \\ \hline B & - & S & 2 & 5 & 5 & 4 & 6 \\ \hline C & - & S & 3 & 4 & 6 & 3 & 5 \\ \hline D & A B & 1 & 4 & 2 & 4 & 1 & 3 \\ \hline E & B & 2 & 5 & 3 & 2 & 2 & 4 \\ \hline F & E & 5 & End & 3 & 4 & 1 & 5 \\ \hline G & C, E & 3 & End & 6 & 2 & 4 & 10 \\ \hline H & D & 4 & End & 3 & 3 & 1 & 5 \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|c|c|} \hline ID 7 & Preceding & Start & End & Activity & Staff & Optimisfic & Pessimistic \\ Activity & Activity & Node & Node & Time & Requised & Time & Time \\ \hline A & - & S & 1 & 3 & 4 & 2 & 4 \\ \hline B & - & S & 2 & 5 & 5 & 4 & 6 \\ \hline C & - & S & 3 & 4 & 6 & 3 & 5 \\ \hline D & A B & 1 & 4 & 2 & 4 & 1 & 3 \\ \hline E & B & 2 & 5 & 3 & 2 & 2 & 4 \\ \hline F & E & 5 & End & 3 & 4 & 1 & 5 \\ \hline G & C, E & 3 & End & 6 & 2 & 4 & 10 \\ \hline H & D & 4 & End & 3 & 3 & 1 & 5 \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started