Dream Team Productions, a firm hired to coordinate the release of the movie Paycheck (starring Uma Thurman and Ben Affleck), identified 16 activities to be
- Dream Team Productions, a firm hired to coordinate the release of the movie Paycheck(starring Uma Thurman and Ben Affleck), identified 16 activities to be completed before the release of the film. The tasks (in time units of weeks) are as follows:
Activity | Immediate Predecessors | Optimistic Time | Most Likely Time | Pessimistic Time |
A | - | 1 | 2 | 4 |
B | - | 3 | 3.5 | 4 |
C | - | 10 | 12 | 13 |
D | - | 4 | 5 | 7 |
E | - | 2 | 4 | 5 |
F | A | 6 | 7 | 8 |
G | B | 2 | 4 | 5.5 |
H | C | 5 | 7.7 | 9 |
I | C | 9.9 | 10 | 12 |
J | C | 2 | 4 | 5 |
K | D | 2 | 4 | 6 |
L | E | 2 | 4 | 6 |
M | F, G, H | 5 | 6 | 6.5 |
N | J, K, L | 1 | 1.1 | 2 |
O | I, M | 5 | 7 | 8 |
P | N | 5 | 1 | 9 |
a) How many weeks in advance of the film release should Dream Team have started its marketing campaign? What is the critical path?
b) If activities I and J were not necessary, what impact would this have on the critical path and the number of weeks needed to complete the marketing campaign?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started