Question

1 Approved Answer

Dummy activities A . have a duration equal to the shortest non - dummy activity in the network. B . cannot be on the critical

Dummy activities
A. have a duration equal to the shortest non-dummy activity in the network.
B. cannot be on the critical path.
C. are found in both AOA and AON networks.
D. are used when two activities have identical starting and ending events.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Stephen P. Robbins, Mary Coulter, Ed Leach, Mary Kilfoil

12th Canadian Edition

0134830458, 978-0134830452

More Books

Students also viewed these General Management questions