Question

1 Approved Answer

During 2020,SageCompany started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021

During 2020,SageCompany started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available.

2020

2021

2022

Costs incurred to date$380,000$847,770$1,069,000Estimated costs to complete620,000253,230-0-Billings to date302,000896,0001,610,000Collections to date272,000812,0001,418,000

(a)

New attempt is in progress. Some of the new entries may impact the last attempt grading.

Your answer is incorrect.

Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Gross profit recognized in 2020$

enter a dollar amount

Gross profit recognized in 2021$

enter a dollar amount

Gross profit recognized in 2022

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Accounting

Authors: Kevin R Callahan, Gary S Stetz, Lynne M Brooks

2nd Edition

1118078209, 9781118078204

More Books

Students also viewed these Accounting questions

Question

1. Why do we trust one type of information more than another?

Answered: 1 week ago