During the startup phase of a project, the typical margin of error for effort estimates based on data collected from past projects is... 25% to
During the startup phase of a project, the typical margin of error for effort estimates based on data collected from past projects is... 25% to 50% Less than 5% 0.25x to 4x of the actual effort 10% to 20%