Each of three mutually exclusive projects costs $200. Using the table provided, rank the projects in descending NPV order. Present Value Interest Factor Projects' Cash
Each of three mutually exclusive projects costs $200. Using the table provided, rank the projects in descending NPV order. Present Value Interest Factor Projects' Cash Flow Year (10%) A B C 1 .91 $300 $200 $ 0 2 .83 200 100 100 3 .75 100 0 100 4 .68 0 100 200 5 .62 0 200 300