Answered step by step
Verified Expert Solution
Question
1 Approved Answer
each week given and schedules-shown in Table 7-4. When a task spans more than one week, the costs should be divided equally among the weeks.
each week given and schedules-shown in Table 7-4. When a task spans more than one week, the costs should be divided equally among the weeks. Task 12. A project consists of three tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 3. Task B is scheduled to begin at the start of Week 1 and finish at the end of Week 2. Task C is sched- uled to begin at the start of Week 2 and end at the end of Week 3. The budgeted cost for Task A is $22,000, for Task B is $17,000, and for Task C is $15,000. At the end of the second week, Task A is 65% complete, Task B is 95% complete, and Task C is 60% complete. What is the SPI for the project at the end of the second week? 13. A project consists of six tasks. Task A is scheduled to be- gin at the start of Week 1 and finish at the end of Week 4. Task B is scheduled to begin at the start of Week 1 and Table 7-3 Data for Problem 10 Mobilization Grubbing Rough Excavate Roadway Grade and Roll Sub Grade Place and Compact Road Base Place and Compact Asphalt Grade Shoulders Clean Up Demobilize Cost ($) 1,000 4,000 24,000 1,000 8,000 12,000 1,000 1,000 1,000 Start 1 2 4 5 5 6 6 6 Week Finish 1 4 5 5 1 6 6 finish at the end of Week 2. Task C is scheduled to be- gin at the start of Week 3 and end at the end of Week 4. Task D is scheduled to begin at the start of Week 1 and end at the end of Week 1. Task E is scheduled to begin at the start of Week 2 and end at the end of Week 4. Task F is scheduled to begin at the start of Week 4 and end at the for Task B is $2,000, for Task C is $3,000, for Task D is end of Week 4. The budgeted cost for Task A is $10,000, $1,000, for Task E is $6,000, and for Task F is $4,000. At the end of the third week, Task A is 80% complete, Task B is 100% complete, Task C is 40% complete, Task D is 100% complete, Task E is 55% complete, and Task F has not started. What is the SPI for the project at the end of the third week? 14. The ACWP at the end of the second week for the project in Problem 12 is $37,900. Determine the CPI for the project. 15. The ACWP at the end of the third week for the project in Problem 13 is $16,500. Determine the CPI for the project. 16. Determine the total estimated cost at completion and estimated cost to complete for the project in Problem 14, assuming the CPI remains the same through the remain- der of the job. 17. Determine the total estimated cost at completion and estimated cost to complete for the project in Problem 15, assuming the CPI remains the same through the re- mainder of the job. 6 18. Mt. Ogden Homes started out five years ago building a few homes a year. During the last few years, they have
questions 14 and 16 please.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started