Question
1 Approved Answer
EARNED VALUE ANALYSIS * end of 6th week WEEK Planned Value* RP Earned Value ACTIVITY 1 2 3 4 5 6 7 8 9 10
EARNED VALUE ANALYSIS | |||||||||||||||
* end of 6th week | |||||||||||||||
WEEK | Planned Value* | RP | Earned Value | ||||||||||||
ACTIVITY | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | |||
Initial meeting with project sponsors | $15,000 | $15,000 | 100% | ||||||||||||
Draft project requirements | $23,000 | $9,000 | $32,000 | 100% | |||||||||||
Review with stakeholders | $4,000 | $8,000 | $12,000 | 100% | |||||||||||
Develop and approve project charter | $9,000 | $9,000 | 100% | ||||||||||||
Develop WBS | $12,000 | $12,000 | 100% | ||||||||||||
Estimate durations | $13,000 | $13,000 | 100% | ||||||||||||
Assign resources | $8,000 | $8,000 | $4,000 | $16,000 | 75% | ||||||||||
Determine task relationships | $8,000 | $8,000 | 50% | ||||||||||||
Enter cost information | $16,000 | $16,000 | 25% | ||||||||||||
Review plan with stakeholders | $8,000 | $0 | 0 | ||||||||||||
Review off-the-shelf training materials | $23,000 | $0 | 0 | ||||||||||||
Negotiate contract for materials | $24,000 | $16,000 | $0 | 0 | |||||||||||
Develop communications for new training | $18,000 | $0 | 0 | ||||||||||||
Create survey to determine needs | $24,000 | $0 | 0 | ||||||||||||
Administer survey | $12,000 | $0 | 0 | ||||||||||||
Develop list of training instructors | $6,000 | $12,000 | $0 | 0 | |||||||||||
Setup classrooms | $30,000 | $30,000 | $0 | 0 | |||||||||||
Schedule courses | $4,000 | $2,000 | $8,000 | $0 | 0 | ||||||||||
Develop system for signing up for classes | $16,000 | $0 | 0 | ||||||||||||
Develop course evaluation form | $20,000 | $0 | 0 | ||||||||||||
BAC (total budget for the project) | |||||||||||||||
Weekly Planned Value (PV) | |||||||||||||||
Cumulative Planned Value (PV) | |||||||||||||||
Weekly Actual Cost (AC) | $17,000 | $25,000 | $13,000 | $30,000 | $46,000 | $9,000 | |||||||||
Cumulative Actual Cost (AC) | |||||||||||||||
Weekly Earned Value (EV) | |||||||||||||||
Cumulative Earned Value (EV) | |||||||||||||||
Project EV as of Week 6 | |||||||||||||||
Project PV as of Week 6 | |||||||||||||||
Project AC as of Week 6 | |||||||||||||||
CV = EV - AC | |||||||||||||||
SV = EV - PV | |||||||||||||||
CPI = EV/AC | |||||||||||||||
SPI = EV/PV | |||||||||||||||
Estimate At Completion (EAC)=BAC/CPI | |||||||||||||||
Estimated Time to Complete=OTE/SPI | weeks |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started