Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

ELECTRON CORPORATION Review this case carefully and answer the questions at the end of tile case in detail. You are the contracting officer in charge

ELECTRON CORPORATION Review this case carefully and answer the questions at the end of tile case in detail. You are the contracting officer in charge of administering a $3,550,000 firm-fixed-price contract with the Electron Corporation. The contract calls for the manufacture of 530 electronic reading machines. It contains general provisions, a normal schedule and a Federal Specification describing the reading machine. This specification, in general, is a performance specification containing numerous performance requirements and an elaborate set of test procedures and test results which must be complied with to achieve satisfactory performance. In addition, the specification calls for a large number of specific electronic components which must be used by the contractor. The delivery schedule allows approximately two months for design of the reading machine (first delivery is eight months after the contract date and the lead time for several of the electronic components is six months). The contract was let to Electron after competitive negotiation in which Electron submitted the third low proposal out of eight companies. The procurement contracting officer rejected the two lower offerors on technical and management grounds and had negotiated Electron down in price by $165,000. After six weeks of work on the contract, the Contract Manager of Electron asks you to attend a conference at which various people in the company are going to discuss the progress to date on this contract. At the conference, on March 15, it appears that the Engineering Department is having some difficulty in completing the design on time - the difficulty seems to be that several of the circuits have failed to their initial testing with the result that systems tests cannot be undertaken in accordance with the original design schedule. After a thorough discussion the various department heads decide to delay the manufacturing schedule by one month but to order the specified long lead time components in order to assure that the contract delivery schedule will be met. Three weeks later, on April 5, the Contract Manager and the Director of Engineering of Electron present you with the facts. Continued difficulties have been encountered in the engineering process and the cause seems to be several of the specified electronic components. The Director of Engineering is quite certain that the reading machine could be made to meet the test specifications if newer (and more expensive) components are used. He suggests that you issue a change to the specifications substituting these components at an estimated price increase of $430,000 (including $180,000 termination charges for long lead time components already on order). You immediately submit the request to your technical branch with a request that they furnish an expeditious answer since time is vital to the contractor at this stage of performance. Two days later your technical people tell you that they do not object to the substitution of the components at no increase in price. However, they assert that the contractor's difficulty is really one of circuitry which he does not want to redesign. They point out that the development contractor of this electronic reading machine, Neutron Company, used the specified components on their development model and successfully completed almost all of the tests in the specification without too much difficulty. They also pointed out that the use of Electron's suggested components will eventually raise the costs of the government since the specified components are in stock and hence maintenance costs during operation would be cheaper if the original specification is followed. When you present the facts to Electron personnel, they are quite incensed and point out that the Neutron development mode) was developed to an earlier model of the specification which did not include all of the tests specified in the present specification. They do admit, however, that improvements could be made in the reading machine with a redesign of the circuitry but that such an effort would take six weeks and would cost over $500,000. They express a willingness to undertake such a redesign if the government is willing to order it by a change to the contract.

QUESTIONS: I. What action would you take in these circumstances? Why? 2. What responsibilities has the government assumed in this procurement? 3. Would your answer be different if the contract had been awarded through, a sealed bid procurement process? why' or why not?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Venture capital and the finance of innovation

Authors: Andrew Metrick

2nd Edition

9781118137888, 470454709, 1118137884, 978-0470454701

More Books

Students also viewed these Finance questions