Question

1 Approved Answer

Elliot Ltd signs a contract on 30 June 2020, agreeing to build a building for Erica Ltd at contract price of $280,000. Erica Ltd will

Elliot Ltd signs a contract on 30 June 2020, agreeing to build a building for Erica Ltd at contract price of $280,000. Erica Ltd will have the control of the asset throughout the construction process. Elliot Ltd estimates the construction cost will be as follows:

Year ending

Cost

30 June 2021

50,000

30 June 2022

80,000

30 June 2023

20,000

Total

150,000

As the end of its reporting period 30 June 2021, Elliot Ltd had incurred labour costs of $20,000 and materials costs of $40,000. All materials and labour costs were used during the year. As at 30 June 2021, Erica had made progress payments to Elliot Ltd of $100,000.

Required

Calculate the revenue to be recognised by Elliot Ltd for the year ended 30 June 2021 and prepare the journal entries related to the revenue.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

ISE Financial Accounting

Authors: Robert Libby, Patricia Libby, Frank Hodge Ch

11th Edition

1265083924, 9781265083922

More Books

Students also viewed these Accounting questions