Question
Entries and Schedules for Unfinished Jobs and Completed Jobs Staircase Equipment Company uses a job order cost system. The following data summarize the operations related
Entries and Schedules for Unfinished Jobs and Completed Jobs
Staircase Equipment Company uses a job order cost system. The following data summarize the operations related to production for April 2014, the first month of operations:
Materials purchased on account, $2,150.
Materials requisitioned and factory labor used:
Job | Materials | Factory Labor | ||
No. 301 | $2,680 | $1,940 | ||
No. 302 | 3,270 | 2,620 | ||
No. 303 | 2,170 | 1,280 | ||
No. 304 | 7,340 | 4,810 | ||
No. 305 | 4,660 | 3,670 | ||
No. 306 | 3,400 | 2,330 | ||
For general factory use | 910 | 2,870 |
Factory overhead costs incurred on account, $5,120.
Depreciation of machinery and equipment, $1,380.
The factory overhead rate is $50 per machine hour. Machine hours used:
Job | Machine Hours | |
No. 301 | 40 | |
No. 302 | 42 | |
No. 303 | 24 | |
No. 304 | 83 | |
No. 305 | 24 | |
No. 306 | 40 | |
Total | 253 |
Jobs completed: 301, 302, 303, and 305.
Jobs were shipped and customers were billed as follows: Job 301, $7,940; Job 302, $9,590; Job 303, $13,490.
Required:
1. Journalize the entries to record the summarized operations. For a compound transaction, if an amount box does not require an entry, leave it blank or enter "0".
Entries | Description | Debit | Credit |
---|---|---|---|
a. | SelectAccounts PayableCashFactory OverheadFinished GoodsMaterialsWork in ProcessItem 1 | ||
SelectAccounts PayableCashFactory OverheadFinished GoodsMaterialsWork in ProcessItem 3 | |||
b. | SelectAccounts PayableCashCost of Goods SoldMaterialsWages PayableWork in ProcessItem 5 | ||
SelectAccounts PayableAccounts ReceivableCashFactory OverheadMaterialsWages PayableItem 8 | |||
SelectAccounts PayableAccounts ReceivableCashFactory OverheadMaterialsWork in ProcessItem 11 | |||
SelectAccounts PayableCost of Goods SoldFactory OverheadFinished GoodsWork in ProcessWages PayableItem 14 | |||
c. | SelectAccounts PayableCashCost of Goods SoldFactory OverheadMaterialsWork in ProcessItem 17 | ||
SelectAccounts PayableCashCost of Goods SoldFactory OverheadMaterialsWork in ProcessItem 19 | |||
d. | SelectAccounts PayableAccumulated Depreciation-Machinery and EquipmentCashCost of Goods SoldFactory OverheadWork in ProcessItem 21 | ||
SelectAccounts PayableAccumulated Depreciation-Machinery and EquipmentCashFactory OverheadFinished GoodsWork in ProcessItem 23 | |||
e. | SelectAccounts PayableAccounts ReceivableCashFactory OverheadFinished GoodsWork in ProcessItem 25 | ||
SelectAccounts PayableCashFactory OverheadFinished GoodsMaterialsWork in ProcessItem 27 | |||
f. | SelectAccounts PayableAccounts ReceivableCashFactory OverheadFinished GoodsWork in ProcessItem 29 | ||
SelectAccounts PayableCashFactory OverheadFinished GoodsMaterialsWork in ProcessItem 31 | |||
g. | SelectAccounts ReceivableCashFactory OverheadFinished GoodsSalesWork in ProcessItem 33 | ||
SelectAccounts ReceivableCashFactory OverheadFinished GoodsSalesWork in ProcessItem 35 | |||
SelectAccounts ReceivableCost of Goods SoldFactory OverheadFinished GoodsSalesWork in ProcessItem 37 | |||
SelectAccounts ReceivableCost of Goods SoldFactory OverheadFinished GoodsSalesWork in ProcessItem 39 |
2. Post the appropriate entries to T accounts for Work in Process and Finished Goods, using the identifying letters as transaction codes. Insert memo account balances as of the end of the month.
Work in Process | |||
---|---|---|---|
Select(a)(b)(c)(d)(f)(g)Item 41 | Select(a)(b)(c)(d)(e)(f)(g)Item 43 | ||
Select(a)(c)(d)(e)(f)(g)Item 45 | |||
Bal. |
Finished Goods | |||
---|---|---|---|
Select(a)(b)(c)(d)(e)(f)(g)Item 48 | Select(a)(b)(c)(d)(e)(f)(g)Item 50 | ||
Bal. |
3. Prepare a schedule of unfinished jobs to support the balance in the work in process account.
Staircase Equipment Company Schedule of Unfinished Jobs | ||||||||
---|---|---|---|---|---|---|---|---|
Job | Direct Materials | Direct Labor | Factory Overhead | Total | ||||
SelectNo. 301No. 302No. 303No. 304No. 305Item 53 | $ | $ | $ | $ | ||||
SelectNo. 302No. 303No. 304No. 305No. 306Item 58 | ||||||||
Balance of Work in Process, April 30 | $ |
4. Prepare a schedule of completed jobs on hand to support the balance in the finished goods account.
Staircase Equipment Company Schedule of Completed Jobs | ||||||||
---|---|---|---|---|---|---|---|---|
Job | Direct Materials | Direct Labor | Factory Overhead | Total | ||||
SelectFinished Goods, April 30 (Job 303)Finished Goods, April 30 (Job 305)Finished Goods, April 30 (Job 306)Item 64 | $ | $ | $ | $ |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started