Estimating probability of project completion using normal distribution 1PERT analysis indicates that a project has a mean completion time of 40 weeks , with a

Estimating probability of project completion using normal distribution

1PERT analysis indicates that a project has a mean completion time of 40 weeks, with a standard deviation of 2.8 weeks. Probability that the project can be finished in 35 weeks: P(X<35)

2Probability that the project will take longer than 42 weeks: P(X>42)

3Probability that the project will take between 39 to 45 weeks to be completed: P(39

4Probability that the project will be finished after 38 weeks: P(X>38)

5You must quote a delivery date to your client. If you wish to have a 97% service level (i.e., 97% chance that you will finish the project by that date), how many weeks from the start of the project should you set as that completion date?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Personal Financial Planning For Executives And Entrepreneurs

Authors: Michael J. Nathanson, Jeffrey T. Craig, Jennifer A. Geoghegan, Nadine Gordon Lee, Michael A. Haber, Seth P. Hieken, Matthew C. Ilteris, D. Scott McDonald, Joseph A. Salvati, Stephen R. Stelljes

1st Edition

3030405273, 978-3030405274

More Books

Students also viewed these Finance questions