EX-3. - NEWBEE Construction Company began operations in 2017. Construction activity for 2017 is shown below. NEWBEE uses the cost-recovery method Contract......Contract Price...Billings Through 12-31-2017........Collections
EX-3. - NEWBEE Construction Company began operations in 2017. Construction activity for 2017 is shown below. NEWBEE uses the cost-recovery method
Contract......Contract Price...Billings Through 12-31-2017........Collections Through 12-31-2017.............Costs to 12-31-2017........Estimated cost to Complete.
1 .....................P 3,200,000..........................P 3,150,000...........................................P 2,600,000..........................................P 2,150,000 ...........................................0.
2.........................3,600,000...............................1,500,000............................................1,000,000..................................................820,000.................................P 1,880,000
3........................3,300,000...............................1,900,000............................................1,800,000...............................................2,250,000.....................................1,200,000
1. Which of the following should be shown on the income statement for 2017 related to Contract 1?
2. Which of the following should be shown on the statement of financial position at December 31, 2017 related to Contract 2?
3. Which of the following should be shown on the statement of financial position at December 31, 2017 related to Contract 3?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started