Example: A company has the following data for one of its manufacturing cells: Theoretical velocity 20 units per hour Productive minutes available per year 1,200,000

Example: A company has the following data for one of its manufacturing cells:

Theoretical velocity 20 units per hour
Productive minutes available per year 1,200,000
Annual conversion cost $4,800,000
Actual velocity 15 units per hour

Actual cycle time = 60 minutes/15 units = 4 minutes per unit Standard cost per minute = $4 per minute Actual conversion cost per unit = $4 4 = $16 per unit Theoretical cycle time = 60 minutes/20 units = 3 units per hour Theoretical conversion cost per unit = $4 3 = $12 per unit

What we can see from this example is that the company has an incentive to reduce cycle time. It actually takes 4 minutes per unit but it could take as little as 3 minutes per unit. If cycle time could be reduced, the number of units produced could be increased and conversion cost per unit could be decreased. If actual cycle time were decreased to 3.5 minutes per unit, actual velocity (rounded to the nearest whole unit) would be $ _____units per hour, and actual conversion cost would be $______per unit.

Manufacturing cycle efficiency (MCE) is another measure of operating efficiency.

MCE = Processing time/(Processing time + Move time + Inspection time + Waiting time + Other non-value-added time)

Example: A company provided the following information for one of its products for each hour of production:

Actual velocity: 50 units per hour
Move time: 10 minutes
Inspection time: 5 minutes
Rework time: 15 minutes

Processing time = 60 minutes 10 minutes 5 minutes 15 minutes = 30 minutes MCE = 30/60 = 0.5

This MCE of 0.5 tells the company that 50% of the time is value-added processing time and the other 50% is waste. The company now has an incentive to reduce the non-value-added time. Suppose that quality were increased and rework time was reduced to 5 minutes. The new MCE (rounded to two significant digits) would be _____.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions