EXERCISE 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Rates LO2-4 Finishing and Fabrication are $18.00 per direct labor-hour and i
EXERCISE 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Rates LO2-4 Finishing and Fabrication are $18.00 per direct labor-hour and i 10% of direct materials cost, respectively. The labor wage rate is $16.00 per hour. The following information pertains to Job 700: Finishing Fabrication Direct materials $410 $60 Direct labor $128 $48 Required: 1. What is the total manufacturing cost assigned to Job 700