The following information relates to a project of the Cumberland Construction Company: 2016 2017 2018 Actual total costs incurred to date $136,000 $616,000 $882,000 Estimated

The following information relates to a project of the Cumberland Construction Company:

2016

2017

2018

Actual total costs incurred to date

$136,000

$616,000

$882,000

Estimated costs to complete

714,000

264,000

--

The contract price was $1,200,000. Cumberland uses the cost-to-cost method of revenue recognition.


What are the TOTAL estimated costs for the contract in 2016? _______________

How much revenue should be recognized in 2016? $__________

How much gross profit should be recognized in 2016? $­­­___________

Step by Step Solution

3.36 Rating (162 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Supply Chain and Operations An Integrative Approach

Authors: Thomas Foster, Scott E. Sampson, Cynthia Wallin, Scott W Webb

1st edition

132832402, 978-0132832403

More Books

Students also viewed these Accounting questions

Question

Discuss the three primary responsibilities of a project manager.

Answered: 1 week ago

Question

6.4 Describe the treatment of dissociative identity disorder.

Answered: 1 week ago