FACT SCENARIO E (Questions 19-22): Geddy Construction (GC) has a written contract with Owner, an Oklahoma municipality, to build a sewer treatment plant with three

FACT SCENARIO E (Questions 19-22):

Geddy Construction (GC) has a written contract with Owner, an Oklahoma municipality, to build a sewer treatment plant with three lagoons. The prime contract is governed by the 2017 Edition of AIA Document A201. Owner hired YYZ Design (YYZ) to prepare the plans and specifications. YYZ, in turn, hired an independent lab to perform a comprehensive soils test. Based on the results of the soils test, the plans and specifications prepared by YYZ called for the installation of bentonite-treated clay liners in the three lagoons. The specified mix ratio was 3%. Significant leaks appeared shortly after the lagoons were constructed and filled with water. The project was shut down for 3 months while the source of the leaks and a possible solution were investigated. GC, Owner, and YYZ subsequently determine that the specified bentonite mix ratio of 3% was inadequate to properly seal the floor of the lagoons. At the Owner's request, GC prepares a cost estimate to rework the clay liners with additional bentonite. After receiving GC's cost estimate, the Owner and YYZ decide that GC should have recognized the error in the specifications and reported the problem before the clay liners were first installed. The Owner and YYZ issue a change directive requiring GC to proceed with the remedial work at GC's own expense. In total, the project takes 6 months longer than expected and GC spends $150,000 on the lagoon repairs. YYZ is also the designated Initial Decision Maker (IDM).

Upon receiving the CCD, what steps should GC take to preserve and pursue a claim for additional compensation?

Group of answer choices

Issue a stop work notice until an agreement is reached and a change order, rather than construction change directive, is executed by all parties.

Notify the architect in writing of the disagreement over the CCD, proceed with work, implement a procedure for tracking costs of the extra work, and initiate theclaims process.

Record a lien and file suit to foreclose the lien.

Obtain substitute collateral for the CCD and proceed with the work.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Human Resource Management Text And Cases

Authors: Tom Redman, Adrian Wilkinson

4th Edition

9780273757825

Students also viewed these Law questions