FACT SCENARIO F (Questions 23-27): With regard to the notice and suit filing requirements which must be satisfied by subcontractors and suppliers in order to

FACT SCENARIO F (Questions 23-27):

With regard to the notice and suit filing requirements which must be satisfied by subcontractors and suppliers in order to successfully assert a claim on a prime contractor's public works payment bond under Title 61 Oklahoma Statutes, answer the following:

If notice is required, to whom must it be sent?

Group of answer choices

General Contractor

Surety

Owner and General Contractor

Surety and General Contractor

General Contractor, Surety and Owner

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Employment Law New Challenges In The Business Environment

Authors: John Jude Moran

5th Edition

536067031, 978-0536067036

More Books

Students also viewed these Law questions

Question

Personal role: This consists of service to family and friends.

Answered: 1 week ago