Fill in or solve the questions beneath, and return paper. 3 machines process products with process times per part of (10, 5, 12 ) minutes
Fill in or solve the questions beneath, and return paper. 3 machines process products with process times per part of (10, 5, 12 ) minutes respectively. The transfer batch is 25 between M1 and M2 and 50 between M2 and M3. Parts arrive simultaneously in a batch of 100 parts.
a) Draw a Gantt chart. (4p)
b) How long will it take to completely process all 100 items that came in? (1p) Answers
a) draw Gantt chart underneath
3 machines process products with process times per part of (10,5,12) minutes respectively. The transfer batch is 25 between M1 and M2 and 50 between M2 and M3. Parts arrive simultaneously in a batch of 100 parts. a) uraw a uant cnart. (4p) b) How long will it take to completely process all 100 items that came in? (1p) Answers a) draw Gantt chart underneathStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started