Fill in or solve the questions beneath, and return paper. 3 machines process products with process times per part of (10, 5, 12 ) minutes

Fill in or solve the questions beneath, and return paper. 3 machines process products with process times per part of (10, 5, 12 ) minutes respectively. The transfer batch is 25 between M1 and M2 and 50 between M2 and M3. Parts arrive simultaneously in a batch of 100 parts.

a) Draw a Gantt chart. (4p)

b) How long will it take to completely process all 100 items that came in? (1p) Answers

a) draw Gantt chart underneathimage text in transcribed

3 machines process products with process times per part of (10,5,12) minutes respectively. The transfer batch is 25 between M1 and M2 and 50 between M2 and M3. Parts arrive simultaneously in a batch of 100 parts. a) uraw a uant cnart. (4p) b) How long will it take to completely process all 100 items that came in? (1p) Answers a) draw Gantt chart underneath

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of strategic management

Authors: Charles w. l. hill, Gareth r. Jones

3rd Edition

1111525196, 978-1111525194

More Books

Students also viewed these General Management questions

Question

1. Discuss the various uses for break-even analysis. (L02)

Answered: 1 week ago